ByteDance weighs larger second phase for Brazil data center, Bloomberg says
Bloomberg reports ByteDance is seeking a developer for a second phase at Pecém in Ceará, larger than the 300-megawatt build underway. ByteDance did not respond to Bloomberg.
Key takeaways
- Bloomberg reports, citing unnamed people, that ByteDance is seeking a developer to run a second stage of its Pecém data center project in Ceará, Brazil.
- According to the report, the second phase would be larger than the 300-megawatt project now under construction, and ByteDance is also in early talks about a similar-sized site outside the port.
- ByteDance did not respond to Bloomberg's request for comment, and the expansion rests on that single report.
- Omnia is building the first phase, with work that started in January and first operations planned for the third quarter of 2027, Reuters reported.
- Omnia signed a $2 billion, 20-year wind power supply deal with Casa dos Ventos in May, according to Reuters.
ByteDance, the Chinese owner of TikTok, is considering a larger second stage for its Pecém port complex data center project in the northeastern Brazilian state of Ceará, Bloomberg reported, citing people familiar with the process who asked not to be named. According to the report, the company is looking for a developer to oversee that phase. ByteDance did not respond to Bloomberg's emailed request for comment, and the company has not announced an expansion.
The expansion claim rests on a single original report. Bloomberg's story, republished in Portuguese by Bloomberg Línea, is the only readable source NextFish found for it; TechNode's coverage summarizes the same Bloomberg reporting. NextFish has not independently verified the plan.
What does the Bloomberg report say?
According to Bloomberg's sources, the second phase would be even bigger than the project currently under construction in Ceará, which the report describes as a $10 billion, 300-megawatt facility. The sources also said ByteDance is in early talks with developers about a data center of similar size outside the Pecém port.
The two sites would serve different customers, Bloomberg reported. Data centers at Pecém must export their data to qualify for tax exemptions, while the site outside the port would serve customers in Brazil. TechNode's summary made the same distinction, noting that the port site earns its tax benefits by serving clients outside Brazil.
What is already being built at Pecém?
At an event in Ceará with President Luiz Inácio Lula da Silva, TikTok Brazil's public policy head Monica Guise said the company would invest more than 200 billion reais in a data center near the Pecém port, Bloomberg reported at the time. Guise said TikTok would partner with data center developer Omnia and renewable energy company Casa dos Ventos, and that the facility would run entirely on wind power. She described it as a historic investment for the company in Brazil.
Omnia, the data center platform of Patria Investments, is building and will operate the facility, with ByteDance as its main client, Omnia CEO Rodrigo Abreu told the Brazilian newspaper O Povo in January, when earthworks had started. Reuters reported in May that construction began in January, with first operations planned for the third quarter of 2027 and a gradual ramp-up through 2029.
O Povo also reported that the current project is one of five data centers ByteDance plans for the Pecém complex, and that the hub had received approval from the national council for export processing zones. The investment projected for that wider hub reaches 571 billion reais, according to O Povo. NextFish could not confirm how that figure relates to the second phase described by Bloomberg.
Where will the power come from?
Power supply has been a central question for the site. In April 2025, before the project was announced, Reuters reported that Brazil's national grid operator ONS had initially denied a grid connection request from Casa dos Ventos for a Pecém data center, citing stability concerns. At that time, one Reuters source said initial talks centered on 300 MW, with a possible second phase of up to 900 MW.
In May, Omnia agreed a $2 billion power purchase deal lasting 20 years with Casa dos Ventos, the companies told Reuters. Electricity will be supplied by Casa dos Ventos' Ibiapaba wind complex, rated at 630 megawatts, and by its Dom Inocencio wind farm in neighboring Piaui state. Environmental groups have raised concerns about water use and possible effects on nearby indigenous communities, Reuters reported. Abreu said the project is fully licensed, meets environmental requirements and will need "minimal water use."
Why is Brazil drawing data center investment?
Bloomberg cited industry group Brasscom as saying Brazil's data center capacity has more than doubled since 2022 to above one gigawatt. Lula signed tax measures in September that cut the tax burden on imported servers, processors and network equipment by about a third, according to Bloomberg, although the industry is still waiting for rules on which products qualify. A lawyer quoted by Bloomberg said transmission capacity remains a challenge for plants seeking to connect to the grid. Bloomberg also wrote that voter backlash against data centers in the U.S. midterm elections could slow expansion there and lead developers to look at other locations, such as Brazil.
Questions readers are asking
Has ByteDance confirmed the Brazil expansion?
No. The expansion was reported by Bloomberg, citing people familiar with the process. ByteDance did not respond to Bloomberg's request for comment.
Who is building the current Pecém data center?
Omnia, the data center platform of Patria Investments, is building and will operate it, with ByteDance as the main client, according to Omnia CEO Rodrigo Abreu.
How will the facility be powered?
Omnia signed a 20-year supply deal with Casa dos Ventos for power from wind farms in Ceará and Piaui, the companies told Reuters.
Why would a second site be built outside the port?
Bloomberg reported that Pecém data centers must export data to qualify for tax exemptions, while a site outside the port would serve customers in Brazil.
Sources
- Bloomberg Línea (Bloomberg): ByteDance, proprietária do TikTok, avalia expansão de data center no Brasil
- TechNode: ByteDance reportedly weighs expanding its Brazil data center project
- Bloomberg Línea (Bloomberg): TikTok anuncia investimento de R$ 200 bilhões para construir data center no Brasil
- O Povo: Data center do TikTok inicia obras no Pecém
- Reuters (via The Star): Brazil's Omnia, Casa dos Ventos sign $2 billion energy deal for TikTok data center
- Reuters (via The Star): Exclusive-TikTok owner weighs data center project in Brazil, sources say
- #bytedance
- #data-centers
- #brazil
- #pecem
- #renewable-energy
Get the day's top AI & tech stories on WhatsApp: Follow the NextFish channel
Get stories like this every morning.
Related
Data Centers & Energy2 min
ReNew plans 1 GW green data centre in India's Andhra Pradesh
About ₹67,000 crore is earmarked for the Anakapalli site, part of roughly ₹80,000 crore ReNew announced for the state. Reports name no customer, power contract or completion date.
Data Centers & Energy3 min
Malaysia to require data centres to disclose power use and GPU imports
Trade minister Johari Abdul Ghani says the rule will be written into law so the government can monitor data centres. He also said some imported GPUs had been re-exported.
Chips & Infra3 min
Cerebras names Microsoft as new cloud customer, lifts 2026 outlook
Its results cited a deal with an unnamed top-three hyperscaler; the CEO told CNBC it is Microsoft. Cerebras now expects $940 million to $960 million in 2026 core revenue.
Data Centers & Energy3 min
Anthropic reportedly buys $3.4bn of gas generators for its data centers
The FT says Anthropic took over a supplier's Caterpillar orders for 1.7 gigawatts of generators in late September. Neither company commented, and the deal is unconfirmed.